Whilst it is still my intention to project manage the work myself I am going to get a quote from a main contractor for comparative purposes.

In any event I am going to need a specification of work required so here is my first version of it. It is not particularly detailed in as much as it does not specifiy where light switches should go and what radiators to use but it is a start.

I am sure I will have missed out some major items but you've got to start somewhere.

Outside
  1. Remove / repair / replace all damaged render from left flank wall as required.
  2. Re-point right flank wall as required.
  3. Bond “falling” bricks above the front door.
  4. Clear front and back garden.
  5. Paint all masonry and front door.
Inside
  1. Remove current kitchen, bathroom, fitted wardrobes and cupboards, flooring (not floorboards), electrical fittings and heating / plumbing.
  2. Remove all plaster from front and back rooms to ceiling
  3. Remove plaster as required to all other rooms including back bedroom ceiling.
  4. Repair / replace downstairs joists as required and ensure that they are not touching outside walls.
  5. Repair current stair treads as required.
  6. Install airbricks to provide adequate under floor ventilation.
  7. Install chemical DPC to outside wall in two reception rooms.
  8. Treat all wood for worm etc.
  9. Install new window with lintel to new upstairs bathroom.
  10. Install studwork for new upstairs bathroom and hall.
  11. Install new soil pipe and waste to upstairs bathroom and connect to main drain.
  12. Re-wire house including new fuse box.
  13. Install new boiler and heating system.
  14. Brick up windows no longer required.
  15. Plaster all rooms as required.
  16. Replace / repair skirting board as required.
  17. Replace all windows as specified.
  18. Install and fit new kitchen
  19. Install and fit new upstairs bathroom
  20. Sand downstairs floors if possible.
  21. Re-glaze existing internal doors and re-hang.
  22. Line walls if required.
  23. Install insulation into the loft.
  24. Paint and decorate all rooms
  25. Tile kitchen and bathroom walls and floors as required.
  26. Carpet stairs and bedrooms.
  27. Fit laminate flooring if sanding downstairs floors is not possible.
If anyone can think of items I have doubtless forgotten please let me know.