Monday 5 January 2009

11 Days to Go

According to the project clock we have 11 days to go to finish this project. That isn't going to happen and the end of the month is more likely but will still be tight.

The terms of the insurance policy state that the house must be visited once every seven days so as nobody has been working I paid one visit over the holidays.

As we start the New Year – this is where we are.

  • The bedrooms are largely finished bar final painting and second fix plumbing and electrics. They look really good and more work will be done this week.
  • The bathroom needs to be installed and the new soil pipe run. This is the largest job outstanding upstairs.
  • Stairs – there is some repair work to be done to the stairs.
  • All thermaboard need to be applied downstairs and then plastered. This is will start this week as the materials will be delivered this afternoon.
  • The kitchen needs to be installed.
  • The cloakroom needs to be installed.
  • The new boiler needs to be installed and commissioned.
  • The under stairs cupboard floor needs to be re-laid.
  • Second fix plumbing and electrics need to be completed.
  • The garden needs some more work.
  • The outside brickwork needs to be tidied up and painted.

That's about it although I am sure I have forgotten something.

I still hope to have the house back on the market by the end of the month.